May 2015 – ISS On-Orbit Status Report [1]

[]

Date: 2022-08

Fluid Shifts Baseline Imagery Collection: Kornienko performed his Flight Day 45 baseline imaging for the Fluid Shifts experiment. With Padalka as the onboard imager and ground remote guidance, ultrasound imaging was taken of arterial and venous measures of the head and neck, cardiac, ophthalmic and portal vein, and tissue thickness of lower and upper body. Additional measurements using the Cerebral and Cochlear Fluid Pressure (CCFP), Distortion Product Otoacoustic Emissions (DPOAE), Optical Coherence Tomography (OCT), ESA’s Cardiolab (CDL) Holter Arterial Blood Pressure Device, and Intraocular Pressure (IOP) using the tonometer were taken as well. The imagery session was within the 10 day requirement following last week’s dilution measurements. Next week, both Kelly and Kornienko will be performing the same measurements in the Service Module using the Lower Body Negative Pressure (Chibis) device. Fluid Shifts is a joint NASA-Russian experiment that investigates the causes for severe and lasting physical changes to astronaut’s eyes. Because the headward fluid shift is a hypothesized contributor to these changes, reversing this fluid shift with a lower body negative pressure device is investigated as a possible intervention. Results from this study may help to develop preventative measures against lasting changes in vision and eye damage.

Columbus (COL) Water On-Off Valve (WOOV)6 Removal and Replacement (R&R): Cristoforetti replaced the COL InterFace Heat Exchanger (IFHX) WOOV6. Express Rack 3 was tilted down in order to perform the R&R. Inspection of WOOV6 in April 2013, during WOOV7 replacement, revealed minor corrosion/contamination signs but no operational failures. In August 2014, WOOV6 failed to reach end position during valve cycling but was successfully recovered by direct commanding attempts from COL-CC. Since then the valve has been left in the operational open position. If WOOV6 were to get stuck in the open position, IFHX Low Temperature Loop (LTL) water side hydraulic isolation would not be possible in the event of a water leak.

Tonometer Troubleshooting: Kelly with ground assistance performed troubleshooting of the tonometer following the intermittent readings from the tonometer during his Fluid Shifts session yesterday. Kelly used the tonometer and the eye tonometry simulator to reattempt data collection. Images of the hardware were sent down for ground teams to evaluate prior to the Fluid Shifts Tonometry session for Kornienko later in the day.

Permanent Multipurpose Module (PMM) Post Relocation Outfitting: Kelly installed an Intermodular Ventilation (IMV) Valve on the Node 3 Forward Port Bulkhead to provide PMM with return ventilation. In addition, Kelly and Virts installed new PMM location-code based labels for Fire Ports, Standoffs and Racks to match the ISS coordinate system with PMM at Node 3 Forward.

Today’s Planned Activities

All activities were completed unless otherwise noted.



FS – Hardware Setup

Fluid Shifts – Donning Holter Arterial BP – Subject

ISS crew and ГОГУ (RSA Flight Control Management Team) weekly conference (S-band)

IMS Tagup (S-band)

Solution Crystallization Observation Facility (SCOF) Cable Connection

JEM – CGSE Gas Supply Stop

Installation of inserts for easy opening of SM interior panel locks (panel 429). Structural Elements Kit (004890R, ФГБ1ПГО_4_427_1, CTB No.1112 (004106J))

WRS – Recycle Tank Fill

Installation of inserts for easy opening of SM interior panel locks (panel 433). (Kit with structural elements (004890R, ФГБ1ПГО_4_427_1, CTB No.1112 (004106J))

Inspection of Portable Breathing Apparatus (PBA) and Portable Fire Extinguisher (PFE)

Node3 IMV Valve Installation

Fluid Shifts – Baseline Scan – Subject

Life On The Station Photo and Video

Fluid Shifts – Scan Operator

RGN – Initiate drain into EDV

Removal of Force Loader [НС-1М] Control Unit.

SCOF – Cable Reconfiguration

RGN – Terminate water drain into EDV

Payload CTB Audit

ИК0501 Gas Analyzer О2 readings adjustments. Uout =2.8 V.

LBNP Exercise (PRELIMINARY).

PAO Hardware Setup

Cleaning ВД1 and ВД2 Air Ducts in DC1 WRS – Recycle Tank Fill

Crew Prep for PAO

PAO Event

VCA1 setup and adjustment in Columbus

Express Rack 3 Preparation and Tilt Down

Columbus WOOV6 (Water ON OFF Valve) Replacement

RGN REC-TNK – Remove depress hose for nominal operations

USND2 – Hardware Deactivation

Inspecting RS Structural Elements Shell Surfaces using МВП-2К device.

PMM Relabel

Soyuz 716 Kazbek Fit Check

Preparing for downlink RS shell structural element surface inspection data

OTKLIK. Hardware Check

Installation of inserts for easy opening of SM interior panel locks (panel 430). Structural Elements Kit (004890R, ФГБ1ПГО_4_427_1, CTB No.1112 (004106J))

WRS – Recycle Tank Fill

Fluid Shifts – Tonometer Exam

IMS Delta File Prep

MPCC Laptop deactivation and deinstallation

PK4 – Familiarization. Conference with Investigator (as necessary) / See OSTPV for Procedure

Express Rack 3 Tilt Up

Flight Director / ISS Crew Tagup

Crew conference with Astronaut Office [Aborted]

Completed Task List Items

Journal-Aud-Entry-CDR

Ground Activities

All activities were completed unless otherwise noted



JEMRMS Operations

Three-Day Look Ahead:

Saturday, 05/30: Housekeeping, Off Duty



Sunday, 05/31: Off Duty

Monday, 06/01: FPS Procedure Review and Tool Gather, Microbiome Surface Sampling

QUICK ISS Status – Environmental Control Group:

[END]
---
[1] Url: https://blogs.nasa.gov/stationreport/2015/05/

Published and (C) by NASA
Content appears here under this condition or license: Public Domain.

via Magical.Fish Gopher News Feeds:
gopher://magical.fish/1/feeds/news/nasa/