This unaltered story was originally published by U.S. NASA Space Agency.
URL:
https://www.nasa.gov
Content is in public domain.
------------
ISS Daily Summary Report – 5/21/2022 – ISS On-Orbit Status Report
[]
Date: 2022-05-21 00:00:00
Boeing Orbital Flight Test 2 (Boe-OFT2) Ingress: Docking of the Boeing Crew Space Transportation (CST)-100 Starliner spacecraft was successfully completed yesterday evening, Friday, May 20th, at 7:28 p.m. CT. This morning, the crew opened the hatch at 11:04 a.m. CT. The crew performed initial vehicle leak checks, pressurized the vestibule from ISS, ingressed, and configured Starliner for quiescent operations. Starliner will remain docked to the ISS until Wednesday, May 25th at approximately 1:30 p.m. CT.
Payloads:
eXposed Root On-Orbit Test System (XROOTS): The crew performed a water fill and cleaning activity for the XROOTS plant growth hardware. XROOTS procedures were also reviewed. The plant growth phase of the experiment is currently scheduled to begin next week. The XROOTS investigation uses hydroponic and aeroponic techniques to grow plants without soil or other growth media. Video and still images enable evaluation of multiple independent growth chambers for the entire plant life cycle from seed germination through maturity. Results could identify suitable methods to produce crops on a larger scale for future space missions.
Systems:
In Flight Maintenance (IFM) Oxygen Generation Assembly (OGA) Spare Pump ORU Flush: As part of preventive maintenance, the crew configured hardware for ground-commanded pre-flush followed by flush setup in preparation for Spare OGA Pump Orbital Replacement Unit (ORU) 10L flush. These activities are in preparation for a flush of the Spare OGA Pump ORU to be performed tomorrow. The OGA produces oxygen via electrolysis using iodinated water from the Waste Processor Assembly (WPA), and the Pump ORU circulates water through the OGA.
Completed Task List Activities:
None
Today’s Ground Activities:
All activities are complete unless otherwise noted.
CST-100 VV Processor (RT) Swap
CST-100 C&W Reconfig
OGA Spare Pump Sample and Flush
Medium Temperature Heat Exchanger WOOV Cycling
Node Forward IMV Deactivation
IAS IDA Hardline Configuration
CST-100 Config for Attached Ops
Node 2 Fwd Stbd IMV Fan Activate
Node 2 Headset Extension Cable Setup
C2V2 Video Transmitter Turn On/Off
Crew Dragon Wakeup for CST Voice Checks
Look Ahead Plan
Sunday, May 22 (GMT 142)
Payloads:
Off-Duty
Systems:
EVA Water Containment Activities
OGA Post Maintenance Flush/Stow
Monday, May 23 (GMT 143)
Payloads:
AstroPi Night Setting (ESA)
CAL MTL Jumper Leak Check (NASA)
DECLIC HD Exchange, Alice-like Removal, and Direct Solid Insert (NASA)
NanoRacks Module 63, 83 Photos (NASA)
Vascular Aging Blood Pressure Measurement and Echo Scans (CSA)
XROOTS Nutrient Mix and Fill and Fluid Recovery and Plant Thinning (NASA)
Systems:
OFT-2 Ops
CMS ARED Quarterly Inspection
Tuesday, May 24 (GMT 144)
Payloads:
CBEFL Cable Reconnect (JAXA)
Desiccant swaps (ICEBERG, POLAR, GLACIER) (NASA)
EPM Troubleshoot ops (ESA)
Repository Urine setup (NASA)
Surface Avatar H/W setup
Systems:
IFM UTS Remove & Install
IFM T2 and WRS Sys 1 Rack Prep
WRS CWC-I Degas
OFT-2 Ops
Today’s Planned Activities:
All activities are complete unless otherwise noted.
[END]
[1] Url:
https://blogs.nasa.gov/stationreport/2022/05/21/iss-daily-summary-report-5-21-2022/
Published by NASA.Gov
via Magical.Fish Gopher News Feeds:
gopher://magical.fish/1/feeds/news/nasa/