This unaltered story was originally published by U.S. NASA Space Agency.
URL:
https://www.nasa.gov
Content is in public domain.
------------
Key Milestones After Liftoff – James Webb Space Telescope
[]
Date: 2021-12-24 00:00:00
Both immediately after launch and over the following weeks, the James Webb Space telescope will pass through numerous milestones on its journey of approximately 1 million miles to its final orbit around the second Lagrange point, commonly known as L2.
NASA has a detailed plan to deploy the Webb Space Telescope over a roughly two-week period. For details on any particular milestone – or to get updates on how far along Webb is in the process – please read about the deployments here. You may also watch a visualization.
The process involves hundreds of individual deployments. It is not an automatic, hands-off sequence; it is human-controlled. This means that the order, location, timing, and duration of deployments may change. However, the default order and approximate timing is as follows:
First hour:
Liftoff
~9 minutes: main stage separation
~27 minutes: upper stage separation
~33 minutes: solar array deployed
First Day
~12.5 hours: Midcourse correction burn (MCC1a)
~1 day: Release and motion test of the gimbaled antenna assembly
. . and on
2 days: Midcourse correction burn (MCC1 b)
3 days: Forward sunshield pallet deployment
3 days: Aft sunshield pallet deployment
4 days: Deployable tower assembly
5 days: Aft momentum flap
5 days: Sunshield covers release
6 days: Sunshield port mid-boom and sunshield starboard mid-boom
7 days: Sunshield layer tensioning begins
8 days: Sunshield layer tensioning complete
10 days: Secondary mirror deployment begins and is completed
11 days: Aft Deployed Instrument Radiator
12 days: Port primary mirror wing deployment begins and is completed
13 days: Starboard primary mirror wing deployment begins and is completed
13 days: Webb is fully deployed
15-24 days: Individual mirror segment movements
29 days: Midcourse correction burn (MCC2)/L2 insertion burn
29.5 days: Orbit insertion complete
[END]
[1] Url:
https://blogs.nasa.gov/webb/2021/12/24/key-milestones-after-liftoff/
Published by NASA.Gov
via Magical.Fish Gopher News Feeds:
gopher://magical.fish/1/feeds/news/nasa/