                    Tentative Schedule for the New
                  TELNET Implementation for the TIP

   Implementation of the New TELNET Protocol has now become the top
priority item on the TIP development queue.  Because what is done in the
TIP potentially affects what is done at a number of hosts, below we give
the implementation schedule to which we hope to adhere.

   - July 18, 1975 -- Done with the basic design.  A version of the TIP
     which has a general version of the option negotiator, but refuses
     all options, operational.

   - Mid-September, 1975 -- Design of the options done.  A version of
     the TIP which includes any modifications that are necessary to
     support the options operational.

   - Mid-November -- Operational version of the TIP with the basic set
     of options implemented (Binary Transmission, Echo, Suppress Go-
     Ahead, Timing Mark, RCTE).

   - End of 1975 -- Any problems with hosts worked out, any necessary
     revisions done, and a solid version of the TIP up and running the
     TELNET Protocol with options.










      [ This RFC was put into machine readable form for entry ]
      [ into the online RFC archives by Alex McKenzie with    ]
      [ support from GTE, formerly BBN Corp.            10/99 ]










Walden                                                          [Page 1]