more valves
A leak of nitrogen tetroxide fumes from another faulty
valve on Saturday caused a 45 minute delay in the filtering
process of the propellant.  Workers were evacuated from
pad 39A, but no one was hurt.  Officials say that some
time was lost, but it will not delay the scheduled 4
November launch of the orbiter.

-----------------------------------------------------------------