____________________________________________________________________________
___
Title:      Federal Transit Administration Grant Management
Subtitle:

Report No.: GAO/HR-93-16       Date:  December 1992
____________________________________________________________________________
___
Author:     United States General Accounting Office


Addressee:  High-Risk Series

This file contains the text of a GAO report. Delineations within the text
indicating chapter titles, headings, and bullets are preserved. No attempt h
as
been made to display graphic images or pagination of the typeset report.
Footnotes appear in brackets at the reference point in the text. Underlined
text is indicated by underscore characters (_Introduction_). Superscript
characters are preceeded by a backslash (\a). Figures may be omitted or
replaced with tables. Tables may not resemble those in the printed version.

A printed copy of this report may be obtained from the GAO Documents
Distribution Facility by calling (202) 512-6000 or faxing your request
to (301) 258-4066 or writing to P.O. Box 6015, Gaithersburg, MD 20877.
____________________________________________________________________________
___

____________________________________________________________________________
___

CONTENTS

Overview
     - The Problem
     - The Causes
     - GAO's Suggestions for Improvement
FTA's Grant Programs
Past Oversight Did Not Protect Scarce Federal Transit Funds
     - Grantees' Inadequate Controls and FTA's Ineffective Oversight Placed
Funds At
       Risk
     - FTA Did Not Use Its Monitoring Tools Effectively
     - FTA Has Been Reluctant to Use Its Full Range of Enforcement Tools
FTA Has Charted an Ambitious Course for Implementing Needed Changes
     - FTA's Approach to Oversight Has Changed
     - New Initiatives Parallel GAO Recommendations
     - Recent Legislation Has Addressed Other GAO Concerns
     - Barriers Could Delay the Implementation of New Initiatives
Conclusions and Action Needed
Related GAO Products
High-Risk Series
     - Lending and Insuring Issues
     - Contracting Issues
     - Accountability Issues




















____________________________________________________________________________
___

Office of the Comptroller General
Washington, DC 20548

December 1992

The President of the Senate
The Speaker of the House of Representatives

In January 1990, in the aftermath of scandals at the Departments of Defense
and Housing and Urban Development, the General Accounting Office began a
special effort to review and report on federal government program areas that
we considered "high risk."

After consulting with congressional leaders, GAO sought, first, to identify
areas that are especially vulnerable to waste, fraud, abuse, and
mismanagement. We then began work to see whether we could find the fundament
al
causes of problems in these high-risk areas and recommend solutions to the
Congress and executive branch administrators.

We identified 17 federal program areas as the focus of our project. These
program areas were selected because they had weaknesses in internal controls
(procedures necessary to guard against fraud and abuse) or in financial
management systems (which are essential to promoting good management,
preventing waste, and ensuring accountability). Correcting these problems is
essential to safeguarding scarce resources and ensuring their efficient and
effective use on behalf of the American taxpayer.

This report is one of the high-risk series reports, which summarize our
findings and recommendations. It describes our concerns over the management
and oversight of federal transit grants by the Department of Transportation'
s
Federal Transit Administration. It examines the agency's failure to use its
monitoring and enforcement tools to detect and correct serious, widespread,
and often long-standing noncompliance and inappropriate expenditures of fund
s
by grant recipients. It also discusses new initiatives that the agency is
taking to better safeguard future grants, including implementing most of our
numerous recommendations. We will continue to monitor the agency's progress
to
confirm that the new oversight strategy is in place and achieving its
objectives.

Copies of this report are being sent to the President-elect, the Democratic
and Republican leadership of the Congress, congressional committee and
subcommittee chairs and ranking minority members, the Director-designate of
the Office of Management and Budget, the Secretary-designate of
Transportation, and the Administrator of the Federal Transit Administration.


Signed: Charles A. Bowsher



____________________________________________________________________________
___

OVERVIEW
----------------------------------------------------------------------------
---

The Federal Transit Administration (FTA), within the Department of
Transportation, provides federal grants to help states and localities develo
p
new mass transit systems and operate, maintain, and improve existing ones.
FTA, mostly through its 10 regional offices, is responsible for monitoring
grant recipients in their use of federal funds and enforcing their complianc
e
with federal regulations.

FTA currently administers about 4,400 active grants totaling $35 billion.
Funding for mass transit--and therefore the risk of mismanagement--could gro
w
significantly: Recent legislation has increased authorized annual funding fr
om
$3.2 billion to $5 billion and allowed up to $70 billion in highway funds to
be used for transit needs over the next 6 years. In addition, the current
focus on expanded federal infrastructure investment, including mass transit,
together with a potentially rapid infusion of funds, increases the need for
making wise investments and carefully monitoring federal funding.

============================================================================
===
THE PROBLEM

FTA's ineffective oversight of transit grants has enabled grant recipients t
o
misuse millions of dollars in federal funds. Grant recipients' problems with
financial management, procurement, and inventory control have gone undetecte
d
or uncorrected for as long as a decade or more.

We have documented waste and mismanagement at grant recipients in several FT
A
regions. For example, even after it became apparent that Pittsburgh Port
Authority Transit lacked the engineering skills to complete a nearly $20
million trolley rehabilitation project, FTA's Philadelphia region continued
to
fund the project for several years, without requiring corrective action. In
the San Francisco region, grant recipients spent almost $40 million more in
federal funds on buses than federal guidelines allowed. Although entrusted
with $1.6 billion in active FTA grants, the Chicago Transit Authority, in
FTA's Chicago region, had significant management problems that went
uncorrected for over a decade. In FTA's New York region, a major constructio
n
project at the Long Island Railroad more than doubled in cost--from an
estimated $171 million to nearly $400 million--and was completed 5 years lat
e.

============================================================================
===
THE CAUSES

Until recently, FTA focused its resources on awarding grants rather than on
ensuring their proper use. Although FTA rules call for regular progress
reports, reviews, and audits, FTA monitored recipients superficially and
inconsistently. Furthermore, it seldom used its enforcement powers to compel
recipients to fix problems, even when the recipients had long histories of
noncompliance. Instead, FTA relied primarily on recipients' assurances that
they would manage funds properly. Whether intentionally or not, FTA's "hands
off" approach to oversight conveyed the message that federal grant regulatio
ns
were not important and federal funds did not need to be safeguarded.

============================================================================
===
GAO'S SUGGESTIONS FOR IMPROVEMENT

We have made numerous recommendations for correcting FTA's oversight practic
es
and safeguarding federal transit funds. Among other things, we called for FT
A
to ensure that its grant recipients have adequate management systems,
strengthen its reviews of recipients, and link grant funds to compliance wit
h
rules.

In the spring of 1992, FTA acknowledged the problems cited by GAO and also b
y
the Department of Transportation's Office of Inspector General (OIG). In
August 1992, FTA began implementing an oversight strategy that incorporates
GAO's recommendations. The strategy involves performing annual risk
assessments of each grant recipient, establishing detailed procedures for
monitoring recipients, and adopting a comprehensive enforcement system, amon
g
other actions. In addition, the Federal Transit Act, signed into law in
December 1991, addressed our long-standing concerns with FTA's oversight of
safety and process for awarding discretionary grants.

FTA faces several hurdles in implementing the new oversight strategy; in
particular, it must resolve issues of staffing and use of contractors. FTA
will have to be persistent in its efforts to ensure that implementation of t
he
new strategy does not lose momentum. Successful implementation will ultimate
ly
depend on the support that the administration and the Congress give to FTA's
actions to impose appropriate controls on grant recipients, including taking
enforcement action and withholding funds when warranted against noncompliant
recipients. But if carried out in full, the new strategy should substantiall
y
improve grant recipients' compliance and better safeguard federal transit
dollars.

____________________________________________________________________________
___

FTA'S GRANT PROGRAMS
----------------------------------------------------------------------------
---

FTA provides federal assistance grants for the development of new mass trans
it
systems and for the operation, maintenance, and improvement of existing
systems. Since its inception in 1964, FTA has provided over $67 billion in
transit grants, and it currently administers over 4,400 active grants totali
ng
$35 billion to state and local transit providers (grantees).

Grantees must comply with a variety of rules, including the requirements of
the Federal Transit Act and regulations, such as the Buy America provisions,
that apply to recipients of federal grants. Grantees certify to FTA that the
y
have the ability and intention to meet these requirements. Whereas grantees
are responsible for the day-to-day management of their grants, FTA is
responsible, primarily through its 10 regional offices, for ensuring grantee
s'
compliance with federal requirements and proper use of federal funds.

FTA has many tools for monitoring grantees and enforcing their compliance wi
th
federal requirements. In the past, however, FTA has not taken advantage of
these tools and has instead relied primarily on grantees' certifications of
their intent to comply with grant requirements. Furthermore, FTA has focused
its resources on awarding grants rather than on ensuring the proper use of
grant funds. On the basis of our work and that of the OIG, the Secretary of
Transportation cited FTA's inadequate oversight of grantees as a material
internal control weakness in the Department's Federal Managers' Financial
Integrity Act reports to the President and the Congress for fiscal years 198
9,
1990, and 1991.

____________________________________________________________________________
___

PAST OVERSIGHT DID NOT PROTECT SCARCE FEDERAL TRANSIT FUNDS
----------------------------------------------------------------------------
---

FTA's former approach to oversight clearly placed scarce transit funds in
jeopardy. FTA did not give high priority to overseeing grants; rather, it
relied primarily on assurances by grantees that they would manage federal
funds properly. However, as we and the OIG have documented in numerous
reports, grantees have had serious deficiencies in financial, technical,
procurement, inventory, and other management controls that have resulted in
noncompliance with federal requirements and improper use of grant funds.

Because FTA failed to oversee grantees' activities effectively, such problem
s
often went undetected and uncorrected for up to a decade and longer. This
"hands off" approach to oversight conveyed to grantees--whether intentionall
y
or not--that federal grant regulations were not important and federal funds
did not need to be safeguarded.

============================================================================
===
GRANTEES' INADEQUATE CONTROLS AND FTA'S INEFFECTIVE OVERSIGHT PLACED FUNDS A
T
RISK

We examined grantees' management and FTA's oversight in four FTA regions tha
t
together oversee more than 60 percent of FTA's total active grants. These
reports revealed significant, long-standing deficiencies that had led to
grantees' wasting and misspending federal funds. Our work disclosed the
following:

-- In FTA's Philadelphia region, transit grants were vulnerable to fraud,
  waste, and mismanagement because grantees did not have adequate financial
  and other management systems to ensure compliance with federal requiremen
ts
  and the proper use of funds. For example, Pittsburgh's Port Authority
  Transit did not have (1) adequate inventory controls to prevent the use o
f
  parts purchased with FTA funds for non-FTA purposes or (2) the technical
  engineering skills to complete a nearly $20 million trolley rehabilitatio
n
  project.

When these and other problems were brought to its attention, the region did
not require the grantees to take prompt corrective actions. Indeed, FTA
continued to fund the trolley rehabilitation project for several years after
it was apparent that the project's progress was both costly and slow. We
concluded that the region's "hands off" monitoring stance contributed to the
grantee's violations of FTA rules and inefficient and inappropriate use of
federal grant funds. We made several recommendations to strengthen the
region's oversight and minimize the inappropriate expenditure of federal
transit funds in the future.

-- In FTA's San Francisco region, financial, procurement, and property
  management deficiencies existed at over half of the grantees. These
  deficiencies led to noncompliance with federal grant requirements and
  inappropriate expenditures of federal funds. For example, four of the
  region's grantees did not have adequate property management controls to
  ensure that the number of buses purchased with federal funds complied wit
h
  FTA rules. As a result, according to the OIG, the grantees inappropriatel
y
  spent almost $40 million in federal grant funds to purchase more buses th
an
  their service needs warranted.

Furthermore, the region did not exercise adequate oversight of its grantees'
activities. Although the region did recover some misspent funds, it did not
routinely compel grantees to correct underlying management deficiencies to
prevent future abuses. We concluded that the region must target its oversigh
t
efforts to ensure the adequacy of grantees' management systems and the quick
detection and correction of deficiencies. Without such actions, the region's
grants would remain vulnerable to fraud, waste, and mismanagement. We made
recommendations to improve the reliability of grantees' compliance assurance
s
and to minimize the vulnerability of the region's grants.

-- In FTA's New York region, deficiencies in procurement, quality assurance,
  and other management controls at the Long Island Railroad more than doubl
ed
  costs for a major construction project--from an estimated $171 million to
  nearly
  $400 million--and delayed the project's completion from 1986 to 1991. At
  the New York City Transit Authority, inadequate management controls led t
o
  the waste, misuse, or mismanagement of more than $90 million, as document
ed
  by the OIG over a 4-year period.

Although the region knew about these problems and had frequently instructed
grantees to correct the deficiencies, it did not confirm that corrections we
re
made promptly. Problems continued at both grantees for several years. We
concluded that until the region moved quickly and aggressively to bring
grantees into compliance with federal requirements, funds would continue to
be
misspent. We made several recommendations to improve the region's oversight
of
grants and to ensure grantees' proper use of federal transit funds.

-- In FTA's Chicago region, deficiencies in the Chicago Transit Authority's
  procurement process, capital program management, and financial and
  inventory control systems permitted the misuse and mismanagement of
  millions of dollars.

Although the region was responsible for overseeing more than $1.6 billion in
active grants to the authority, it did not exercise sufficiently rigorous
oversight to detect the magnitude and severity of the management weaknesses.
The region allowed some problems to go uncorrected for over a decade. We mad
e
several recommendations to strengthen the region's oversight and ensure that
grantees have adequate systems for managing their federal transit grants.

Additional information about these problems appears in the reports and
testimonies listed under Related GAO Products at the end of this report.

Work performed by the Department of Transportation's OIG supports our
findings. In 109 reports issued between January 1988 and May 1992, the OIG
documented numerous instances of noncompliance and deficiencies in grantees'
management systems that resulted in the waste, misuse, and mismanagement of
nearly $400 million. For example, the OIG reported that 31 of 48 grantees
examined had overcharged FTA $85.6 million to purchase more buses and bus
parts than FTA's policies allow. The OIG also reported that 36 of 60 grantee
s
examined had charged FTA $50 million for items, such as extended warranties,
that were not eligible for reimbursement under FTA guidelines.

============================================================================
===
FTA DID NOT USE ITS MONITORING TOOLS EFFECTIVELY

The Federal Transit Act and FTA regulations provide numerous tools for
monitoring grantees' activities. These tools include quarterly progress and
financial reports, annual financial audits (called single audits) conducted
by
public accounting firms, comprehensive management reviews (called triennial
reviews) generally conducted at each grantee every 3 years, grant closeout
audits, OIG audits, and procurement system reviews. FTA also uses contractor
s
to monitor grantees' activities. However, FTA has not effectively and
consistently used these tools to verify that grantees have adequate manageme
nt
controls to reasonably ensure compliance with federal requirements and the
proper use of funds.

Descriptions of FTA's principal monitoring tools follow:

-- _Quarterly progress and financial reports_--
  These reports are FTA's most timely source of information about grantees
  and should enable FTA to identify problems, such as cost overruns or
  program delays, and implement appropriate changes before funds are wasted
  or mismanaged. However, FTA has not consistently reviewed the reports'
  contents or even required all grantees to submit reports.

-- _Single audits_--FTA requires its grant recipients to submit copies of
  audits performed pursuant to the Single Audit Act of 1984. The objectives
  of a single audit include determining whether an entity
  1) has internal control systems to provide reasonable assurance that it i
s
  managing federal financial assistance programs in compliance with
  applicable laws and regulations and (2) has complied with the laws and
  regulations that may have a material effect upon each major federal
  financial assistance program.

The audit tests performed to assess compliance with a program's requirements
are suggested by the agency administering the program--in this case the
Department of Transportation--and are compiled in a "compliance supplement"
to
the single audit guidance published by the Office of Management and Budget
(OMB). FTA believes that the single audits have not been particularly useful
in gauging either the adequacy of grantees' internal controls or actual
compliance. FTA attributes these inadequacies to the limited detail on audit
work suggested in the current compliance supplement, which the agency has
targeted for complete revision.

-- _Triennial reviews_--Until recently, FTA headquarters limited the scope a
nd
  depth of triennial reviews and, hence, their usefulness as an oversight
  tool. Although the law calls for "a full review and evaluation of the
  performance of a [grant] recipient in carrying out the recipient's progra
m,
  with specific reference to compliance with statutory and administrative
  requirements," FTA's reviews focused primarily on grantees' certification
s
  and assurances. The reviews included little or no testing for compliance
to
  ensure, for example, that procurement actions had been competitive or tha
t
  grantees had adequate controls over federally funded inventories. In
  several instances, triennial reviews did not detect existing problems. We
  have repeatedly questioned the value of FTA's limited triennial reviews,
  noting that the abbreviated scope could not provide a full and complete
  review of grantees' control systems.

-- _Grant closeouts_--When closing a grant after a project has been complete
d   or terminated, FTA relies on single audits to verify the appropriateness
of
  costs. We have recommended that FTA reassess its practice of relying on
  single audits to verify the appropriateness of costs when closing grants.
  Because the single audit is not grant-specific--it focuses on the grantee
  rather than on individual grants--we continue to believe that its
  usefulness for reconciling completed or terminated grants is limited.

-- _Other monitoring tools_--FTA considers site visits, quarterly progress
  review meetings, procurement system reviews, day-to-day contacts, OIG
  audits, and GAO reports as monitoring tools. However, site visits were
  often made only once every 3 years during triennial reviews, quarterly
  progress reviews were held at a few grantees but not at the majority, and
  only seven procurement system reviews have been conducted since the
  agency's inception even though we and the OIG have repeatedly reported
  problems with grantees' contracting activities. Also, day-to-day contacts
  may supplement other oversight efforts, but they cannot be a substitute f
or
  monitoring grantees' performance. Finally, periodic GAO and OIG reviews d
o
  not relieve FTA of its responsibilities to monitor grantees' compliance o
r
  obviate the need for FTA to detect and correct problems before funds are
  misspent.

-- _Contractor-provided oversight_--FTA has not made full use of contractors
  to augment the oversight performed by its staff. FTA has authority to use
  contractors to provide direct, on-site project management oversight and t
o
  conduct grantee compliance, safety, financial, procurement, and managemen
t
  reviews. For fiscal year 1991, FTA had $35.3 million available to contrac
t
  for oversight assistance but spent only $14.8 million. FTA has no written
  procedures for its staff to use to oversee the contractors' work, and
  responsibility for overseeing contractors rests at FTA headquarters in
  Washington, D.C., rather than in the regions where the work is done. We
  repeatedly recommended that FTA strengthen and properly use its monitorin
g
  tools and contracting authority.

When we surveyed FTA's regions on their use of grant-monitoring tools, we
found no consistency in the level of effort or focus. Some regions dedicated
a
few staff to monitoring grants, while others assigned nearly all staff to at
least some monitoring tasks; some regions gave triennial reviews higher
priority, while others stressed quarterly reports. Ironically, the region
responsible for overseeing the most grant money devoted one-third less time
to
monitoring than the region with the least grant money.

============================================================================
===
FTA HAS BEEN RELUCTANT TO USE ITS FULL RANGE OF ENFORCEMENT TOOLS

In each region we reviewed, we found instances in which long-standing
noncompliance was allowed to continue essentially with impunity. FTA often d
id
not take timely and necessary enforcement actions to compel grantees to
correct problems and usually continued to fund grantees that remained out of
compliance.

FTA's enforcement tools range from sending letters of notice to reducing or
withholding federal funds when federal requirements have not been met or to
seeking reimbursement when funds have been misspent or mismanaged. However,
FTA seldom used its most stringent enforcement tools. Rather, FTA relied
primarily on notification letters and other correspondence, arguing that suc
h
limited action was justified by the continuing nature of the grantee/grantor
relationship. We cautioned FTA that its use of correspondence could not be
considered either timely or appropriate because such notifications failed to
compel grantees to correct noncompliance within a reasonable time. We have
recommended that FTA impose strict sanctions on noncompliant grantees and
insist that corrective actions be taken on significant noncompliance before
new funds are approved. When FTA fails to detect and compel grantees to
correct noncompliance in a timely manner, it suggests to grantees that feder
al
requirements are not important and that grant funds do not need to be
safeguarded.

____________________________________________________________________________
___

FTA HAS CHARTED AN AMBITIOUS COURSE FOR IMPLEMENTING NEEDED CHANGES
----------------------------------------------------------------------------
---

In response to our and the OIG's reports documenting the waste and
mismanagement of federal transit grants, FTA has developed and begun
implementing an oversight strategy that incorporates the majority of our
recommendations to safeguard funds. In addition, the Federal Transit Act,
signed into law in December 1991, addressed our long-standing concerns with
FTA's oversight of safety and process for awarding discretionary grants. [
Footnote 1:  The Federal Transit Act, which is title III of the Intermodal
Surface Transportation Efficiency Act of 1991, amended the Urban Mass
Transportation Act of 1964.  ]  These actions are particularly timely becaus
e
the new law substantially increases FTA's authorized annual funding, raising
it from about
$3.2 billion to about $5 billion. It also allows the use of up to $70 billio
n
in highway funds for transit needs over 6 years.

In our most recent report, we described FTA's new approach to oversight and
the steps that the agency had taken to strengthen grant management. If fully
implemented, the new strategy and mandates would stand as a major
accomplishment resulting from the attention that our high-risk work brought
to
problems in the grant program. However, because the new strategy represents
a
significant departure from FTA's previous oversight approach, the agency wil
l
need to pay close attention to ensure that implementation does not lose
momentum. We will continue to monitor FTA's progress in achieving full
implementation and confirm that the new initiatives provide adequate oversig
ht
of federal transit funds.

============================================================================
===
FTA'S APPROACH TO OVERSIGHT HAS CHANGED

In commenting on drafts of our reports on FTA's regional oversight activitie
s,FTA repeatedly asserted that grantees had adequate internal control system
s,
its own oversight was sufficient, and its enforcement was timely and
appropriate. FTA maintained that we misrepresented the facts, that problems
were the exceptions, and that FTA was aware of and acting on these problems.


Unexpectedly, in the spring of 1992, FTA reversed its position after a task
force, convened by the FTA Administrator, reviewed and confirmed the oversig
ht
deficiencies that we and the OIG had been reporting. The task force agreed
with our assessment that FTA had an adequate assortment of oversight tools b
ut
had not been using them effectively. Recognizing the need "to have an
oversight system in place that provides an acceptable level of stewardship,"
the task force concluded that "a new comprehensive ordering of oversight
priorities and methodologies has to be developed." In May 1992, FTA's
Administrator approved a task force plan to revise grant monitoring and
enforcement practices. FTA now acknowledges that its problems are indeed
extensive and serious and that the agency had not adequately carried out its
fiduciary responsibilities.

============================================================================
===
NEW INITIATIVES PARALLEL GAO RECOMMENDATIONS

We have made 22 recommendations that focus on FTA's (1) ensuring that grante
es
have management systems adequate to account for and protect funds; (2)
requiring that triennial reviews evaluate, analyze, and test grantees'
compliance; (3) using quarterly report data to identify cost, schedule, and
performance problems; (4) coordinating oversight efforts with state and loca
l
audit entities that also oversee grantees;
5) tracking corrective actions on audit findings and withholding funds when
grantees remain out of compliance;
6) resolving significant noncompliance on existing grants before distributin
g
additional funds; and (7) ensuring that contractors have adequate guidance f
or
performing oversight and that resources are appropriately allocated to carry
out oversight tasks. FTA has fully concurred with 18 of these recommendation
s
and concurred in part with the others. FTA has incorporated implementing
actions in its new oversight strategy.

In addition, the new strategy (1) requires an annual risk assessment of each
grantee to target monitoring efforts and resources,
2) uses a matrix developed by the task force to determine the appropriate fo
rm
of oversight for any given circumstance,
3) clearly defines the roles of headquarters and regional offices, (4) makes
use of expanded contracting authority,
5) delineates the specific roles of the single audit and the triennial revie
w,
(6) revises and clarifies guidance for the single audit and the triennial
review, and (7) defines the appropriate form of enforcement necessary to det
er
or remedy grantee noncompliance. The task force also recommended standardizi
ng
policies and guidelines and evaluating staffing levels and the allocation of
personnel at headquarters and in the regions.

The plan signed by the Administrator set an ambitious June 1992 date for ful
ly
implementing the new strategy. FTA did not meet that date. FTA officials
expected that the strategy would be in place in December 1992 and that all
grant oversight activities thereafter would use the new procedures. As part
of
its effort to implement the new strategy, FTA has

-- _revised guidance on single audits_: FTA has reviewed and is revising the
  single audit compliance supplement and other guidance used by private
  accounting firms to ensure that the audits reflect the adequacy of
  grantees' systems and indicate past compliance performance. This exercise
  included developing detailed audit steps needed to assess compliance with
  over 20 standard grant requirements. As we have advised, FTA is working
  with OMB on the compliance supplement, which cannot be implemented withou
t
  OMB's approval.

-- _revised guidance on triennial reviews_: To make more effective use of th
is
  monitoring tool, FTA revised triennial review guidance to ensure that
  procedures measure compliance with all requirements, review efforts focus
  on assembling and analyzing information, and maximum advantage is taken o
f
  the results of other types of monitoring. To further improve the quality
of
  the reviews, FTA plans to provide extensive training for the staff
  performing the triennial reviews.

-- _completed grantee risk assessments_: Regional offices completed risk
  assessments of all grantees scheduled for triennial reviews in fiscal yea
r
  1993. Regional managers are using these risk assessments to develop and
  implement regional oversight plans. These plans will be used by the regio
ns
  to allocate staff and by FTA headquarters to allocate contractor resource
s.

-- _expanded regional office responsibilities_: FTA is working to achieve
  greater consistency in regional offices' approach to project management a
nd
  to provide a minimum level of oversight on each project. As part of this
  effort, FTA is defining, for the first time, the specific roles and
  responsibilities of regional and headquarters personnel in supporting
  oversight efforts.

-- _increased grantee accountability and use of enforcement_: FTA intends to
  hold members of grantees' governing boards and their financial, accountin
g,
  and legal advisors accountable for false or otherwise erroneous
  certifications. FTA is also increasing emphasis on ensuring that grantees
  have the internal audit capabilities to which they certify. At the same
  time, FTA is developing procedures to make full use of enforcement
  authorities, including withholding funds if necessary, and setting time
  limits for correcting continuing violations of grant requirements.

============================================================================
===
RECENT LEGISLATION HAS ADDRESSED OTHER GAO CONCERNS

The Federal Transit Act addressed concerns that we first raised in 1989
regarding FTA's oversight of safety and process for awarding discretionary
grants. In December 1989, we reported that FTA's oversight was not adequate
to
assess safety conditions at a local transit authority and that we were unabl
e
to determine the factors that the FTA Administrator had considered in awardi
ng
section 3 discretionary grants. We recommended that FTA obtain more complete
and accurate information on accidents and maintain documentation on the
section 3 award process. We reiterated our concerns in reports and testimoni
es
during deliberations on the recently enacted Federal Transit Act.

The new law requires a comprehensive report to the Congress on current trans
it
safety conditions. Among other things, that report is to

-- summarize all deaths and injuries to passengers and employees resulting
  from unsafe conditions in any facility, equipment, or operation financed
  with FTA funds;

-- describe the actions that FTA has taken to alert transit operators to
  unsafe conditions and to correct or eliminate such conditions;

-- consider the actions taken by grantees to correct unsafe conditions befor
e
  FTA awards a new grant or makes funds available under existing grants; an
d

-- recommend legislative or administrative actions needed to ensure that gra
nt
  recipients will use the best means available to correct or eliminate
  hazards of death or injury.

The agency has gathered and analyzed data from states and begun to draft an
initial report. Although the law specified that the report was to be issued
by
June 1992, FTA does not expect to issue it until April 1993.

In addition, under the Federal Transit Act, a section 3 grant for a new fixe
d
guideway system--such as a subway line--cannot be made until the Administrat
or
has determined that a proposed project is (1) based on an analysis of
alternatives; (2) justified by its capacity to improve mobility, environment
al
benefits, cost-effectiveness, and operating efficiency; and (3) supported by
an acceptable degree of local financial commitment. The law further requires
FTA to issue guidelines for evaluating these criteria.

============================================================================
===
BARRIERS COULD DELAY THE IMPLEMENTATION OF NEW INITIATIVES

Potential barriers to the successful implementation of FTA's new oversight
initiatives stem from the agency's inconsistent allocation of staff and
inadequate use of contractors for oversight tasks. Although most oversight a
nd
all day-to-day contact with grantees take place in FTA regional offices, the
effort expended on oversight and the focus of oversight activities vary from
region to region. In early fiscal year 1992, the number of regional staff
performing oversight ranged from 2 to 12; the proportion of staff time spent
on oversight ranged from 8 percent to 38 percent; and some regions emphasize
d
triennial reviews while others stressed quarterly reports. A planned study t
o
determine the most appropriate level and mix of staff among regional offices
and headquarters has been postponed until 1994. However, in a September 16,
1992, letter, the Department of Transportation informed us that the FTA
Administrator was examining FTA's organizational structure and would take
steps in the near term to ensure that resources were appropriately allocated
to provide adequate attention to oversight functions.

____________________________________________________________________________
___

CONCLUSIONS AND ACTION NEEDED
----------------------------------------------------------------------------
---

With the support of the Department of Transportation, FTA has made a
commitment to improving grant oversight. This is a marked departure from the
past when FTA relied primarily on grantees' assurances that they would
properly manage federal funds. As FTA begins to monitor grantees' activities
rigorously and to compel timely corrective actions at a few large grantees,
other grant recipients should respond with better self-monitoring. Indeed,
such action will clearly indicate to grantees that FTA is serious about
enforcing compliance with grant requirements and committed to safeguarding
federal transit funds. In addition, since transit needs far outstrip availab
le
funding from all sources--federal, state, or local--more needs can be met wh
en
funds are used efficiently and effectively.

FTA recognizes that a sustained, long-term effort will be needed to fully
implement the new oversight strategy. However, commitment by FTA and the
Department of Transportation alone may not be sufficient. Given the extent t
o
which the new initiatives differ from FTA's past laissez-faire approach to
grant oversight, successful implementation will ultimately depend on the
support that the administration and the Congress give to FTA's efforts to
impose appropriate controls on grantees. Appropriate controls would include
taking enforcement action and withholding funds when warranted against
noncompliant grantees. Support for such action will be particularly importan
t
over the next several years, given the potential for increased funding and a
rapid infusion of federal transit funds.

____________________________________________________________________________
___

RELATED GAO PRODUCTS
----------------------------------------------------------------------------
---

_Mass Transit Grants: If Properly Implemented, FTA Initiatives Should Improv
e
Oversight_ (GAO/RCED-93-8, Nov. 19, 1992).

_Special Report_ on contractor improprieties at an FTA Region II grantee
(GAO/OSI-92-7, Sept. 10, 1992).

_Mass Transit Grants: Risk of Misspent and Ineffectively Used Funds in FTA's
Chicago Region_ (GAO/RCED-92-53, Mar. 4, 1992).

_Mass Transit Grants: Noncompliance and Misspent Funds by Two Grantees in
UMTA's New York Region_ (GAO/RCED-92-38, Jan. 23, 1992).

_Mass Transit Grants: Improved Management Could Reduce Misuse of Funds in
UMTA's Region IX_ (GAO/RCED-92-7, Nov. 15, 1991).

_Mass Transit Grants: Development Time Frames for Selected UMTA Projects_
(GAO/RCED-91-184FS, July 11, 1991).

_Mass Transit Grants: Scarce Federal Funds Misused in UMTA's Philadelphia
Region_ (GAO/RCED-91-107, June 13, 1991).

_Mass Transit: Significant Federal Investment Is Not Adequately Protected_
(GAO/T-RCED-91-68, June 12, 1991).

_Mass Transit: Reauthorization Offers Opportunity to Address the Appropriate
Federal Role_ (GAO/T-RCED-91-41, Apr. 24, 1991).

_Mass Transit: Historical Patterns and Future Outlook_ (GAO/T-RCED-91-15, Ma
r.
5, 1991).

_UMTA Project Oversight and Mass Transit Issues_ (GAO/T-RCED-90-102, Aug. 8,
1990).

_UMTA Project Oversight and Mass Transit Issues_ (GAO/T-RCED-90-103, Aug. 7,
1990).

_Mass Transit Grants: UMTA Needs to Increase Safety Focus at Local Transit
Authority_ (GAO/RCED-90-41, Dec. 1, 1989).

_Mass Transit Grants: UMTA Needs to Improve Procurement Monitoring at Local
Transit Authority_ (GAO/RCED-89-94, Mar. 31, 1989).

____________________________________________________________________________
___

HIGH-RISK SERIES
----------------------------------------------------------------------------
---

============================================================================
===
Lending and Insuring Issues

_Farmers Home Administration's Farm Loan Programs_ (GAO/HR-93-1).

_Guaranteed Student Loans_ (GAO/HR-93-2).

_Bank Insurance Fund_ (GAO/HR-93-3).

_Resolution Trust Corporation_ (GAO/HR-93-4).

_Pension Benefit Guaranty Corporation_ (GAO/HR-93-5).

_Medicare Claims_ (GAO/HR-93-6).

============================================================================
===
Contracting Issues

_Defense Weapons Systems Acquisition_ (GAO/HR-93-7).

_Defense Contract Pricing_ (GAO/HR-93-8).

_Department of Energy Contract Management_ (GAO/HR-93-9).

_Superfund Program Management_ (GAO/HR-93-10).

_NASA Contract Management_ (GAO/HR-93-11).

============================================================================
===
Accountability Issues

_Defense Inventory Management_ (GAO/HR-93-12).

_Internal Revenue Service Receivables_ (GAO/HR-93-13).

_Managing the Customs Service_ (GAO/HR-93-14).

_Management of Overseas Real Property_ (GAO/HR-93-15).

_Federal Transit Administration Grant Management_ (GAO/HR-93-16).

_Asset Forfeiture Programs_ (GAO/HR-93-17).