An administrative law judge has decided that Summit Carbon Solutions should give documents of its “dispersion modeling” to groups that seek them as evidence for the company’s upcoming pipeline permit hearing.
That modeling attempts to predict whether populated areas near the pipeline route would be at risk if the pipeline is breached and releases carbon dioxide.
The gas is an asphyxiant and is toxic at high concentrations. It’s also heavier than air. Under certain weather and topographic conditions, a dense plume of carbon dioxide can travel significant distances.
In 2020, a pipeline break in Mississippi released a plume of carbon dioxide that traveled about a mile to a nearby town. About 200 people were evacuated from the area, and 45 sought treatment at a hospital. No one died.
Dispersion modeling for that pipeline didn’t predict the town was at risk. Such modeling can be expensive and time-consuming.
Summit has resisted requests for the results of its dispersion modeling in Iowa and has argued that the information pertains to safety issues that are governed by federal regulators.
But the Sierra Club of Iowa, the Iowa Farm Bureau Federation and several counties said the models are important for deciding the pipeline’s route, which is governed by the Iowa Utilities Board.
“The IUB needs to know how far the carbon dioxide plume from a leak or rupture of the Summit pipeline would disperse in order to properly approve ‘the location and route’ of the pipeline so as to protect persons and property,” Wally Taylor, a Sierra Club attorney, wrote in a motion to compel Summit to provide the documents.
On Monday, Toby Gordon, an administrative law judge for the Iowa Department of Inspections and Appeals, agreed that the information is likely to be admissible as evidence for the board when it decides whether to issue Summit a pipeline permit.
“I cannot say, as Summit urges, that the dispersion modeling data is irrelevant,” Gordon wrote.
He ordered Summit to provide the documents to the requesters within two days, but the company can appeal.
The final evidentiary hearing for Summit’s project is set to begin in less than a week, and Gordon’s decision was the second in two weeks to compel the company to produce information that might be used as evidence during that hearing. Gordon also said Summit needs to give unredacted copies of its contracts with ethanol plants to attorneys of groups that have sought the information. Summit appealed, and an IUB decision on whether to adopt the order is pending.
There has been a flurry of filings with the IUB as the hearing approaches, along with requests to delay the hearing to allow more time for consideration of the project. Requests for a delay gained new urgency with a recent decision by North Dakota regulators to reject Summit’s proposed route in that state.
It’s unclear how long that might delay Summit’s permit in that state, which is crucial to the company’s project. Its pipeline network would span more than 2,000 miles in five states. It would transport captured carbon dioxide from more than 30 ethanol plants to North Dakota for underground sequestration.
Summit said it will ask the North Dakota State Public Service Commission this week to reconsider its permit application.
“We are one week away,” Jess Mazour, of the Sierra Club, told the IUB at its meeting Tuesday morning. “Just want to remind you that there is still time to delay this hearing and make sure that people have a fair chance in front of the Iowa Utilities Board, because there’s a lot of outstanding things that really should come to a conclusion before we hear Summit’s case and before a decision is made.”
The start date of Summit’s hearing is about nine months earlier than IUB staff initially suggested, according to board documents.
In February, board member Josh Byrnes noted that the board had considered starting in May 2024 and November 2023 before settling on October 2023.
“Trying to rush through this process while maintaining the standard required of the board and board staff is unattainable and could give rise to mistakes and missteps,” he wrote in objection to starting in October. “I understand the desire to keep this case moving and to not cause undue delay; however, that does not mean that we should rush the process.”
But after a change in leadership on the three-person board, Byrnes agreed to an even earlier start date of Aug. 22.
There are pending requests to the board and in court to pause Summit’s permit process. The evidentiary hearing could go for weeks or months.
[END]
---
[1] Url:
https://iowacapitaldispatch.com/2023/08/15/judge-summit-should-reveal-communities-threatened-by-pipeline-leaks/
Published and (C) by Iowa Capital Dispatch
Content appears here under this condition or license: Creative Commons CC BY-ND-NC 4.0.
via Magical.Fish Gopher News Feeds:
gopher://magical.fish/1/feeds/news/iowacapitaldispatch/